Permit Fees
DEPOSITS AND FEE SCHEDULE
FOR WELL AND TEST-HOLE PERMITS
Adopted by Board September
12, 1995
Total Permit Fee -
$275.00
Administrative Fees
Test Hole Permit $25.00
Well Permit
$25.00
Deposits
Test Hole Permit $250.00
Well Permit
$250.00
*An additional $250 expedited
permit fee will be charge for any well drilled within the same day as the
issuance of the permit unless a field technician is available and all needed
forms are on file.
If a test hole permit is issued and all District Rules
are complied with there will be no administrative fee for the first well
permit; the test hole permit deposit will be transferred to the first well
permit. The second well permit will require a deposit but no administrative
fee.
Test hole permits are valid for
forty-five (45) Days. Extension of time may be applied for by applicant.
See NPGCD Rule 9 for extension of time.
Well Permits are valid for
one-hundred-twenty (120) days. Extension of time may be applied for by
applicant. See NPWD Rule 9 for this
procedure.
EXTENSIONS ARE NOT AUTOMATIC!! Test Hole Permits and Well
Permits are considered EXPIRED on the expiration date unless requests for
extensions have been timely and properly filed with the District. Well Permit
extensions are reviewed by the Board of Directors, therefore, requests should
be made in as timely a manner as possible.
Refund Policy:
100% ($250) of the Well or Test Hole Permit Deposit will be refunded if:
1. The Application for
Well or Test Hole Permit is denied, or
2. Log of well and pump information or
test hole log and plugging report is returned within thirty (30) days after
expiration date of permit, or
3. Permit is canceled, by the applicant, before
expiration date. See NPGCD Rule 13 for deposit refund information.
|